FPSO Parque das Baleias

Client: JP Morgan bank

Region: Brazil

Office: Southampton

Lender’s technical consultant, completing technical due diligence in advance of finance closing.

Monitoring of project progress during delivery phase with regular written reports to the

Lenders to support drawdowns.

Site visits throughout construction phase.

press to zoom

press to zoom
1/1

Lender’s technical consultant, completing technical due diligence in advance of finance closing.


Scope included:

· Technical due diligence of proposed FPSO design (hull conversion, topsides & spread mooring system);

· Review of project execution plans, schedule, budget, key project participants & workload;

· Review of key project construction, charter and operations/maintenance contracts;

· Delivery of due diligence report & handling of Lender’s clarifications.


Monitoring of project progress during delivery phase with regular written reports to the


Lenders to support drawdowns.


Site visits throughout construction phase.